Law.com Subscribers SAVE 30%

Call 855-808-4530 or email [email protected] to receive your discount on a new subscription.

EDS Loses to BSkyB in Major Technology Case

By Peter Brudenall
April 28, 2010

In a major decision of London's Technology and Construction Court that will have global repercussions, technology vendor Electronic Data Systems (“EDS” ' now part of Hewlett-Packard (“HP”)) has been found liable for a deceitful misrepresentation that induced broadcaster BSkyB to enter into a contract with it. Although the case did not create any new law, it is the clearest example of an English court finding, in the context of the outsourcing and IT services industry, that pre-contract assurances and promises can amount to deceit, and in this case leading to a damages award well above the agreed liability cap.

As a result, the case will lead to IT and outsourcing service providers, both in the UK and globally, reviewing their pre-contract sales processes, and how they manage bids and promote their services to potential customers. Customers too will be more mindful of pre-contract discussions, and the potential for such discussions to be given greater weight in the event that the contract is unsuccessful. It is also possible that bid costs for major outsourcing contracts will increase as a result of the decision, and that vendors will increasingly deem particularly complex IT projects as too risky.

Background

In July 2000, BSkyB chose EDS to run a new Customer Relationship Management (CRM) project, designed to create an advanced customer service system for its Scottish call centers. In winning the contract, EDS had beaten, among others, PriceWaterhouseCoopers (PWC). As is all too common with major IT projects, the implementation of the system did not go smoothly, and deadlines started slipping. Initially, the parties tried to deal with these issues by essentially putting the project on hold, and then undertaking a re-planning exercise for the rest of the project. As a result, the parties entered into a “Letter of Agreement” that superseded the original contract, and which also purported to exclude liability for all claims up to that point. However, this also proved unsatisfactory, and in 2002 BSkyB ended the contract. In March 2002, BSkyB then took over the project, and in August 2004, it began legal proceedings against EDS. The project was eventually completed in 2006, some five years late and at a cost of over '200 million, nearly six times the cost quoted by EDS.

The Suit

BSkyB claimed that EDS was deceptive, as EDS had made certain representations knowing they were false or at least being reckless as to their truth. These representations related to EDS overselling the CRM system by describing the system as “proven” when it was not, by overstating its capabilities in relation to resources and implementation methodologies, and by understating the amount of time and cost required to implement the system. BSkyB also alleged negligent misrepresentation and breach of contract. Under English law, BSkyB needed to successfully establish fraudulent misrepresentation in order to circumvent the contractual limitation of liability provision, which was capped at '30 million, and to enable it to claim wider, potentially unlimited, damages, including loss of profits. Also under English law, a successful claim for fraudulent misrepresentation allows both foreseeable and unforeseeable damages to be claimed.

BSkyB said that, were it not for EDS's misrepresentation, BSkyB would have awarded the contract to PwC instead of EDS. The latter, however, argued that BSkyB had no definite idea of what it wanted from the project and continually altered its requirements, resulting in delays and other problems. These are typical issues that arise in IT contract disputes, with many failed technology procurements relating to issues around the quality of the systems or services being provided by the vendor and to the changing requirements given by the customer.

The Court's Findings

Although the court rejected certain of BSkyB's allegations of fraudulent misrepresentation (including EDS's costing of the project and capability), it found that EDS was deceitful, first, when it claimed that it had carried out a proper analysis of the time needed to complete the initial delivery and go-live and, second, when it claimed that it held (on reasonable grounds) the opinion that it could and would deliver the project within the promised timescales. The court found that these representations were made dishonestly by EDS's key witness, the CRM Manager, who was discredited when it was revealed that he had also lied about his academic background. The court held that the CRM Manager knew that there had not been the “proper analysis” and that there were not “reasonable grounds” for the opinion that the work would be completed on time, but that he nonetheless made the claims to BSkyB in an effort to win the business.

The Verdict

BSkyB successfully proved that EDS had breached the contract ' and the court held in its favor in relation to contract damages up to the liability cap. BSkyB also proved that liability for non-fraudulent negligent misrepresentations made outside the contract were not properly excluded by the contract, but those again were subject to the liability cap. In early February, the court asked EDS to make an interim damages payment of '200 million, indicating that the final quantum of damages would be far in excess of this amount. To date, that final amount has yet to have been determined.

EDS/HP has indicated it is likely to appeal the judgment. The grounds for such an appeal, its duration and the outcome still are all very uncertain at this time.

Key Issues for Vendors and Customers

Will this “open the floodgates” to similar claims? This is unlikely. The case breaks no legal ground, meaning that it is still a difficult test for an aggrieved customer to satisfy. A customer seeking to bring a claim similar to BSkyB's will still need to establish that a vendor knowingly or recklessly misrepresented its capabilities during the bidding process, as well as the requisite elements of reliance and damage. Given that IT disputes are inevitably complex and extremely expensive to litigate anyway (and therefore rarely reach the courts), this decision is unlikely to lead to any significant increase in similar claims, although we would expect that customers who are in dispute with their IT vendors will increasingly look to the pre-contract discussions to see whether any misrepresentations might have been made. If so, such representations can be used to give the customer significant leverage in the dispute, given the potential liability that could follow.

Should IT vendors now impose protocols and constraints on their sales staff? This is an approach likely to be adopted by many IT vendors in an attempt to minimize risk at the source through the introduction of new sales behaviors rather than having to subsequently rely on legal defenses. Bid teams are likely to be more closely monitored and all aspects of their bids first subjected to internal legal scrutiny.

Will the decision lead to customers seeking only to contract with the larger vendors and on a more defensive contractual basis? Customers are likely to want to obtain sufficient validation for claims made by vendors prior to the contract being signed. It may only be the larger vendors with longer track records that can satisfy these stricter requirements. In addition, customers may seek to contract more defensively, and shift even more risk onto vendors relating to the latter's understanding of the scope of the project and the customer's requirements. In the aftermath of this judgment, vendors may find that unless they are able to give confident and demonstrable assurances around claims made prior to a contract being signed, they will score poorly during the tender process.

More specifically, vendors will need to:

  • Introduce increased monitoring of sales staff and pre-contract behaviors in order to avoid the risk of misleading their customers;
  • Vet communications with a potential customer to eliminate any hasty or poorly considered assurances or promises that could provide ammunition for a future deceit claim;
  • Err on the side of caution, and where customers are proposing a particularly complex project, or one that involves business-critical services, vendors may be reluctant to provide customers with a prediction of success;
  • Utilize their legal team at an early stage in the contracting process to audit the sales process much more closely than has previously been the case, especially on large or vulnerable projects. Marketing briefs, sales documents and bid documents should all be reviewed by legal advisers;
  • Try to ensure the “entire agreement” clause in the contract is clear about excluding liability in relation to pre-contractual representations. The provision as drafted between the parties in this case stated that the Agreement superseded pre-contractual discussions, but did not have the effect of withdrawing such representations and therefore BSkyB was still able to rely on them. There is much case law around entire agreement clauses and vendors will need to be clear about the effect they want the contract and any pre-contractual discussions to have;
  • Avoid commencing provision of the services subject to a Letter of Intent, as during these early phases of a project, it is not unusual for the parties to make numerous oral and written representations about the nature of the project;
  • Conduct an appropriate level of due diligence on the project to ensure that any risks are fully understood;
  • Look at options around insurance for liability for fraudulent or negligent misrepresentations;
  • Be realistic with customers about the potential for a complex IT project to go wrong ' even if this means that more vendors will pull out of procurements if it appears there is even a small risk of it going wrong; and
  • Ensure staff are trained on the implications of this case, and understand the potential for massive liabilities from incorrect or misleading statements made to a customer.

Customers may now seek to bring in arguments of deceit and misrepresentation against service providers. Even if they are unlikely to pursue such claims, it will raise the threat of a claim above the liability cap in the contract. They may exercise more diligence when running tenders (during the RFP process), including asking their service providers to provide firm evidence to support statements made in tender responses, including particularly dates for delivery. As such, service providers may need to work harder to justify their sales claims. Customers may fully document the process for selection so that any promises or statements made by the vendor that were important for the selection process are recorded.

Conclusion

The cumulative effect of this case may be to increase the overall cost of IT and outsourced services contracts, as both customers and vendors devote a greater amount of time to understanding the project, assessing risks and conducting detailed and lengthy due diligence exercises.


Peter Brudenall is a partner in the London office of Hunton & Williams LLP, and is a member of the firm's Global Technology and Outsourcing Practice. Brudenall can be reached at [email protected] or +44 (0)20 7220 5725.

In a major decision of London's Technology and Construction Court that will have global repercussions, technology vendor Electronic Data Systems (“EDS” ' now part of Hewlett-Packard (“HP”)) has been found liable for a deceitful misrepresentation that induced broadcaster BSkyB to enter into a contract with it. Although the case did not create any new law, it is the clearest example of an English court finding, in the context of the outsourcing and IT services industry, that pre-contract assurances and promises can amount to deceit, and in this case leading to a damages award well above the agreed liability cap.

As a result, the case will lead to IT and outsourcing service providers, both in the UK and globally, reviewing their pre-contract sales processes, and how they manage bids and promote their services to potential customers. Customers too will be more mindful of pre-contract discussions, and the potential for such discussions to be given greater weight in the event that the contract is unsuccessful. It is also possible that bid costs for major outsourcing contracts will increase as a result of the decision, and that vendors will increasingly deem particularly complex IT projects as too risky.

Background

In July 2000, BSkyB chose EDS to run a new Customer Relationship Management (CRM) project, designed to create an advanced customer service system for its Scottish call centers. In winning the contract, EDS had beaten, among others, PriceWaterhouseCoopers (PWC). As is all too common with major IT projects, the implementation of the system did not go smoothly, and deadlines started slipping. Initially, the parties tried to deal with these issues by essentially putting the project on hold, and then undertaking a re-planning exercise for the rest of the project. As a result, the parties entered into a “Letter of Agreement” that superseded the original contract, and which also purported to exclude liability for all claims up to that point. However, this also proved unsatisfactory, and in 2002 BSkyB ended the contract. In March 2002, BSkyB then took over the project, and in August 2004, it began legal proceedings against EDS. The project was eventually completed in 2006, some five years late and at a cost of over '200 million, nearly six times the cost quoted by EDS.

The Suit

BSkyB claimed that EDS was deceptive, as EDS had made certain representations knowing they were false or at least being reckless as to their truth. These representations related to EDS overselling the CRM system by describing the system as “proven” when it was not, by overstating its capabilities in relation to resources and implementation methodologies, and by understating the amount of time and cost required to implement the system. BSkyB also alleged negligent misrepresentation and breach of contract. Under English law, BSkyB needed to successfully establish fraudulent misrepresentation in order to circumvent the contractual limitation of liability provision, which was capped at '30 million, and to enable it to claim wider, potentially unlimited, damages, including loss of profits. Also under English law, a successful claim for fraudulent misrepresentation allows both foreseeable and unforeseeable damages to be claimed.

BSkyB said that, were it not for EDS's misrepresentation, BSkyB would have awarded the contract to PwC instead of EDS. The latter, however, argued that BSkyB had no definite idea of what it wanted from the project and continually altered its requirements, resulting in delays and other problems. These are typical issues that arise in IT contract disputes, with many failed technology procurements relating to issues around the quality of the systems or services being provided by the vendor and to the changing requirements given by the customer.

The Court's Findings

Although the court rejected certain of BSkyB's allegations of fraudulent misrepresentation (including EDS's costing of the project and capability), it found that EDS was deceitful, first, when it claimed that it had carried out a proper analysis of the time needed to complete the initial delivery and go-live and, second, when it claimed that it held (on reasonable grounds) the opinion that it could and would deliver the project within the promised timescales. The court found that these representations were made dishonestly by EDS's key witness, the CRM Manager, who was discredited when it was revealed that he had also lied about his academic background. The court held that the CRM Manager knew that there had not been the “proper analysis” and that there were not “reasonable grounds” for the opinion that the work would be completed on time, but that he nonetheless made the claims to BSkyB in an effort to win the business.

The Verdict

BSkyB successfully proved that EDS had breached the contract ' and the court held in its favor in relation to contract damages up to the liability cap. BSkyB also proved that liability for non-fraudulent negligent misrepresentations made outside the contract were not properly excluded by the contract, but those again were subject to the liability cap. In early February, the court asked EDS to make an interim damages payment of '200 million, indicating that the final quantum of damages would be far in excess of this amount. To date, that final amount has yet to have been determined.

EDS/HP has indicated it is likely to appeal the judgment. The grounds for such an appeal, its duration and the outcome still are all very uncertain at this time.

Key Issues for Vendors and Customers

Will this “open the floodgates” to similar claims? This is unlikely. The case breaks no legal ground, meaning that it is still a difficult test for an aggrieved customer to satisfy. A customer seeking to bring a claim similar to BSkyB's will still need to establish that a vendor knowingly or recklessly misrepresented its capabilities during the bidding process, as well as the requisite elements of reliance and damage. Given that IT disputes are inevitably complex and extremely expensive to litigate anyway (and therefore rarely reach the courts), this decision is unlikely to lead to any significant increase in similar claims, although we would expect that customers who are in dispute with their IT vendors will increasingly look to the pre-contract discussions to see whether any misrepresentations might have been made. If so, such representations can be used to give the customer significant leverage in the dispute, given the potential liability that could follow.

Should IT vendors now impose protocols and constraints on their sales staff? This is an approach likely to be adopted by many IT vendors in an attempt to minimize risk at the source through the introduction of new sales behaviors rather than having to subsequently rely on legal defenses. Bid teams are likely to be more closely monitored and all aspects of their bids first subjected to internal legal scrutiny.

Will the decision lead to customers seeking only to contract with the larger vendors and on a more defensive contractual basis? Customers are likely to want to obtain sufficient validation for claims made by vendors prior to the contract being signed. It may only be the larger vendors with longer track records that can satisfy these stricter requirements. In addition, customers may seek to contract more defensively, and shift even more risk onto vendors relating to the latter's understanding of the scope of the project and the customer's requirements. In the aftermath of this judgment, vendors may find that unless they are able to give confident and demonstrable assurances around claims made prior to a contract being signed, they will score poorly during the tender process.

More specifically, vendors will need to:

  • Introduce increased monitoring of sales staff and pre-contract behaviors in order to avoid the risk of misleading their customers;
  • Vet communications with a potential customer to eliminate any hasty or poorly considered assurances or promises that could provide ammunition for a future deceit claim;
  • Err on the side of caution, and where customers are proposing a particularly complex project, or one that involves business-critical services, vendors may be reluctant to provide customers with a prediction of success;
  • Utilize their legal team at an early stage in the contracting process to audit the sales process much more closely than has previously been the case, especially on large or vulnerable projects. Marketing briefs, sales documents and bid documents should all be reviewed by legal advisers;
  • Try to ensure the “entire agreement” clause in the contract is clear about excluding liability in relation to pre-contractual representations. The provision as drafted between the parties in this case stated that the Agreement superseded pre-contractual discussions, but did not have the effect of withdrawing such representations and therefore BSkyB was still able to rely on them. There is much case law around entire agreement clauses and vendors will need to be clear about the effect they want the contract and any pre-contractual discussions to have;
  • Avoid commencing provision of the services subject to a Letter of Intent, as during these early phases of a project, it is not unusual for the parties to make numerous oral and written representations about the nature of the project;
  • Conduct an appropriate level of due diligence on the project to ensure that any risks are fully understood;
  • Look at options around insurance for liability for fraudulent or negligent misrepresentations;
  • Be realistic with customers about the potential for a complex IT project to go wrong ' even if this means that more vendors will pull out of procurements if it appears there is even a small risk of it going wrong; and
  • Ensure staff are trained on the implications of this case, and understand the potential for massive liabilities from incorrect or misleading statements made to a customer.

Customers may now seek to bring in arguments of deceit and misrepresentation against service providers. Even if they are unlikely to pursue such claims, it will raise the threat of a claim above the liability cap in the contract. They may exercise more diligence when running tenders (during the RFP process), including asking their service providers to provide firm evidence to support statements made in tender responses, including particularly dates for delivery. As such, service providers may need to work harder to justify their sales claims. Customers may fully document the process for selection so that any promises or statements made by the vendor that were important for the selection process are recorded.

Conclusion

The cumulative effect of this case may be to increase the overall cost of IT and outsourced services contracts, as both customers and vendors devote a greater amount of time to understanding the project, assessing risks and conducting detailed and lengthy due diligence exercises.


Peter Brudenall is a partner in the London office of Hunton & Williams LLP, and is a member of the firm's Global Technology and Outsourcing Practice. Brudenall can be reached at [email protected] or +44 (0)20 7220 5725.

This premium content is locked for Entertainment Law & Finance subscribers only

  • Stay current on the latest information, rulings, regulations, and trends
  • Includes practical, must-have information on copyrights, royalties, AI, and more
  • Tap into expert guidance from top entertainment lawyers and experts

For enterprise-wide or corporate acess, please contact Customer Service at [email protected] or 877-256-2473

Read These Next
Major Differences In UK, U.S. Copyright Laws Image

This article highlights how copyright law in the United Kingdom differs from U.S. copyright law, and points out differences that may be crucial to entertainment and media businesses familiar with U.S law that are interested in operating in the United Kingdom or under UK law. The article also briefly addresses contrasts in UK and U.S. trademark law.

The Article 8 Opt In Image

The Article 8 opt-in election adds an additional layer of complexity to the already labyrinthine rules governing perfection of security interests under the UCC. A lender that is unaware of the nuances created by the opt in (may find its security interest vulnerable to being primed by another party that has taken steps to perfect in a superior manner under the circumstances.

Strategy vs. Tactics: Two Sides of a Difficult Coin Image

With each successive large-scale cyber attack, it is slowly becoming clear that ransomware attacks are targeting the critical infrastructure of the most powerful country on the planet. Understanding the strategy, and tactics of our opponents, as well as the strategy and the tactics we implement as a response are vital to victory.

Legal Possession: What Does It Mean? Image

Possession of real property is a matter of physical fact. Having the right or legal entitlement to possession is not "possession," possession is "the fact of having or holding property in one's power." That power means having physical dominion and control over the property.

Removing Restrictive Covenants In New York Image

In Rockwell v. Despart, the New York Supreme Court, Third Department, recently revisited a recurring question: When may a landowner seek judicial removal of a covenant restricting use of her land?